Conditional grantDecided 07 July 2023Carlow County Council

2360083: Planning permission is sought for the construction of a one & a half storey style extension to the rear of the existing dwelling, the installation of a new wastewater treatment system and all associated site development works. Retention Permission is also sought for the as-built detached domestic shed

Donore, Bagenalstown, Co. Carlow
DecisionConditional grant
Decided07 July 2023
Application typePERMISSION
Source documents5

Site

What is on file

0refusal reasons10conditions8nearby records

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason

No refusal reason is on record for this application yet.

Conditions

  • 1Development must be carried out in accordance with plans received by the Planning Authority on 17/05/2023, except where altered by conditions.Compliance
  • 2The domestic shed must be used solely for a purpose incidental to the enjoyment of the dwelling. It cannot be used as a self-contained dwelling unit or for any business, trade, or commercial activity.Occupancy
  • 3External wall and roof finishes of the extension must follow Drawing Ref: J843-PL01-001 with a neutral-coloured smooth sand/cement render. The natural stone finish on the existing house must be retained and repaired/reinstated using locally sourced natural stone.Design Materials
  • 4Lines of sight at the new entrance must comply with D.M.R.B. The roadside verge must remain unobstructed. No interference with the public road/footpath without Municipal District Engineer agreement. Road opening works require a Road Opening Licence per ‘Guidelines for Managing Openings in Public Roads (2017)’ submitted for written agreement prior to commencement.Traffic Access
  • 5Minimum one flush out valve on the fully pumped soil polishing filter. System and filter constructed per Drawing Ref. J843-PL03-001 and EPA Code of Practice (PE ≤ 10, June 2021). Prior to occupation, a Certificate of Compliance signed by a qualified person with site-specific 'as-constructed' drawings must be submitted. System tested per I.S. EN 12566. Surface water must not infiltrate the system. A domestic grease trap shall be installed. The existing system shall be decommissioned once the new system operates.Wastewater Drainage
  • 6Development shall not impair existing drainage. No surface water runoff to the public road or adjoining properties. All surface water disposed of to on-site soakways/system per B.S. 8301:1985 and BRE Digest 365 with inspection covers. Only clean surface water to soakpits/system; foul/soiled water to the on-site wastewater treatment system.Water Services
  • 7Adequate off-carriageway parking for construction traffic; no road parking. Prevent debris on the public road. Maintain a neat, litter-free site with skips on site. Noise and dust emissions must not significantly impair amenities beyond the site boundary.Construction Management
  • 8Construction hours restricted to Monday-Friday 08.00-18.00 and Saturday 08.00-13.00. No building activity on Sundays & Bank Holidays.Construction Management
  • 9Prior to commencement, consult the Chief Fire Officer and strictly comply with any fire safety requirements relating to the development.Compliance
  • 10Development contribution of €374.40 for the existing shed (31.2m2) paid within one month of permission. €787.20 for the proposed extension (65.6m2) paid prior to commencement. Interest at 5% p.a. applies after the first 90 days.Development Contribution