2460419: For the re-construction of a section of an existing riverside retaining wall to the Barrow Canal adjacent to junction of R705 and L3044, in the townland of Dunleckny, Bagnelstown. The development will consist of the re-construction of a section of an existing riverside retaining wall, approximately 12m long, which has partially collapsed. The new section of retaining wall shall be constructed in reinforced concrete with stone cladding to match the existing stone retaining wall. An Ecological Impact Assessment and a Natura Impact Statement have also been prepared in respect of the proposed works and submitted with the application.
Barrow Canal, adjacent to junction of R705 and L3044, Dunleckny Bagenalstown
DecisionConditional grant
Decided19 February 2025
Application typePERMISSION
Source documents5
Site
What is on file
0refusal reasons6conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason on record
No refusal reason is on record for this application yet.
Conditions
- 1No surface water from development to be dispersed onto public roadway.Wastewater Drainage
- 2Traffic Management Plan required before site commencement.Construction Management
- 3No construction materials to be stored on public road.Construction Management
- 4Public roads to be kept clear of construction debris.Construction Management
- 5No interference with footpath/road without Municipal Engineer approval.Construction Management
- 6Road Opening License required for any road openings.Construction Management
Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on www.eplanning.ieSource portal
- Notification Of DecisionSource: carlowcoco.eplanning.ie / 683c757c-fba1-4b75-84a9-f14ccc6b2248.pdf / Document 129126Source PDF
- Chief Executives OrderSource: carlowcoco.eplanning.ie / D8ae28f4-5860-4c7f-9ebe-5147f67f371d.pdf / Document 129125Source PDF
- Final GrantSource: carlowcoco.eplanning.ie / 0d9d5356-ba80-4471-8b28-6a6fe560d88d.pdf / Document 130639Source PDF
- Planners ReportSource: carlowcoco.eplanning.ie / Ae579348-1973-429c-8198-bb8825ac6f81.pdf / Document 129168Source PDF
Nearby precedent
Similar nearby applications linked to this planning decision.- 21217Application for extension of duration of planning permission for the refurbishment and re-use of part of Dunleckney Maltings, Bagenalstown, a protected structure. It is proposed to refurbish building 4 (323 sq m) for re-use as an enterprise centre, ancillary to the existing primary industrial use, to include visitor reception, visitor facilities, promotion of industrial building including maltings and brewing. The proposed works will include the removal of the following: modern rainwater goods; upper floor of timber and concrete; timber and metal shutters; blockwork infill to openings, together with all existing building services to Building 4, and modern kiosk and weighbridge. It is proposed to refurbish Building 4 with the installation of insulated composite panel corrugated metal roofing, timber windows to the existing openings and unblocked openings, install a new raised insulated timber floor to the ground level using salvaged boards, form six new openings fitted with glazed doors, install two external ramps and internal ramp and timber decks to the south and west sides, install a mezzanine level, sanitary facilities, kitchen and reception / servery, clad out the existing mass concrete buttresses in brick to match with signage to form main entrance, new paving to the courtyard, installation of new parking facilities for sixteen cars including two accessible spaces, parking for a coach, bicycles, external lighting, bunded oil storage tank behind fencing, new foul drainage underground pump unit and connection into main drainage. / 0.2 km away / 04 August 2021Granted
- 2460312To construct a dormer style dwelling house, new site entrance, connect to public sewer and water mains, all ancillary site works and services / 0.2 km away / 26 May 2025Granted
- 247To construct a 1543sqm training all weather artificial turf pitch with surrounding 6.0m fencing and access gates and 4no. 10.0m flood light poles and all associated site works on existing tennis courts / 0.3 km away / 28 March 2024Granted
- 2440To construct bicycle shelter and associated site works / 0.3 km away / 31 October 2024Granted
- 221921. erect two of 8.0M height flood light poles to the existing training area and associated works. 2 Erect PV Solar Panels on the roof of existing club house and associated works / 0.3 km away / 16 September 2022Granted
- 21321For a stand-alone studio outbuilding within the grounds of Dunleckney Glebe House ancillary and associated with the residential use of the main building. Dunleckney Glebe House is a protected structure RPS reference CW276 / 0.4 km away / 02 February 2022Granted
- 20127For the single storey extension constructed to the rear of the dwelling and all associated development works / 0.4 km away / 04 November 2020Granted
- 22186The construction of a portal frame Grain storage unit and all associated site development works / 0.4 km away / 29 July 2022Granted