18304: For the development of a battery energy storage system (BESS) within a total site area of up to 0.62 hectares, to include 1 no. single storey electrical substation building, 1 no. customer switchgear container, 15 no. electrical inverter/transformer station modules (SKIDS), 10 no. containerised battery storage modules on concrete support structures, 20 no. heating, ventilation and air conditioning units (HVAC units), access tracks and upgraded site entrance, associated electrical cabling and ducting, security gates, perimeter security fencing, CCTV security monitoring system, culvert, landscaping works and all associated ancillary infrastructure on land
Mucklagh, Ballyconnell, Co. Cavan
DecisionConditional grant
Decided24 October 2018
Application typePERMISSION
Source documents7
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason
No refusal reason is on record for this application yet.
Conditions
No conditions
No conditions are on record for this application yet.
Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on www.eplanning.ieSource portal
- Chief Executives OrderSource: cavancoco.eplanning.ie / 4d3200a0-39db-4fd0-8ae6-0a4c3ffb39a0.PDF / Document 317758Source PDF
- Chief Executives OrderSource: cavancoco.eplanning.ie / A1538c2f-e248-47c4-ace1-ed66f7b942f8.PDF / Document 319625Source PDF
- Final GrantSource: cavancoco.eplanning.ie / 88c303be-365c-4cb5-b2d0-677113a6364a.PDF / Document 320463Source PDF
- Planners ReportSource: cavancoco.eplanning.ie / 402e75ff-e563-4142-b7aa-b9df042d1f01.PDF / Document 317756Source PDF
- Planners ReportSource: cavancoco.eplanning.ie / 818597a5-9a60-4094-8d29-2d155b4e6c7d.PDF / Document 319622Source PDF
- F I Request LetterSource: cavancoco.eplanning.ie / 7c8c44d5-8db8-4a3e-9d83-eca4a72af76d.PDF / Document 317759Source PDF
Nearby precedent
Similar nearby applications linked to this planning decision.- 2460072To apply for thirty-year permission for a grid system services facility located at Gortawee, Mucklagh, Ballyconnell, County Cavan, over an area of c.3.46 hectares. The proposed works shall consist of the installation and operation of energy storage units, including 1no. customer switchgear containers and compound, which will be connected to the national grid via the adjacent Gortawee 110kV substation infrastructure, electrical transformers and inverter units, underground cabling and ducting, boundary fencing, security entrance gates, CCTV, internal access road and all associated ancillary infrastructure on land / 0.1 km away / 24 April 2024Conditional grant
- 17282For development at Aughrim Mucklagh Quarry Complex for the continuation of quarrying on some of the lands covered by a previous time limited planning consent PL02.206783 to include extraction from two distinct limestone quarries and a shale quarry, with progressive restoration of the development site and the complete rehabilitation of a former shale quarry, over a 20 year period. The development includes lateral development of the two limestone quarries and a shale quarry employing existing practices, environmental mitigation measures and associated works extending over some 60 hectares of the 107.7 hectare site. The application is accompanied by an Environmental Impact Statement / 0.3 km away / 14 November 2017Conditional grant
- 2227For the erection of 2 no. fully enclosed fuel storage tanks proposed for the refuelling of the Applicant's internal transport fleet. Each tank will have an outer bund which has in excess of 110% of tank capacity and will be sited upon a Concrete Apron with a Class 1 Full Retention Oil Interceptor. Significant further information and revised plans have been submitted. / 0.4 km away / 05 October 2022Conditional grant
- 18244For development consisting of alterations, extension and change of use to Slieve Rushen House to form a Heritage and Ecological Visitor Centre, including toilet facilities, café, information display etc and meeting rooms and 1 no. self catering apartment with associated improvements and upgrade to the existing vehicular access and provision of new car-parking, picnic area and play-park and connection to the public sewer / 0.6 km away / 01 August 2018Conditional grant
- 19200To construct 1 No. Poultry House together with all ancillary structures and all associated site works arising from the above proposed development. Significant further information and revised plans have been submitted / 0.6 km away / 16 January 2020Conditional grant
- 2560506- RED III - for a solar energy development comprising ground mounted solar photovoltaic (PV) panels, mounted on steel support structures, underground cabling, temporary construction compound, erection of Transformer station (11kV), laying of a permeable gravel access track, widening of existing site (field) entrance, relocation of the existing ESB overhead line, erection of CCTV poles and cameras, erection of an entrance gate, artificial berm, landscaping and biodiversity measures all associated ancillary development works, for the purpose of generation renewable energy electricity. Planning Permission is sought for 35-year operation of the solar farm following which the site will be decommissioned, all development removed and the Site restored to agricultural lands / 0.7 km away / 02 December 2025Conditional grant
- 2660165For: the surfacing of the existing hardstanding gravel areas to the north and west of the existing distribution facility, the provision of a designated parking area for HGVs and a staff car park in these areas together with all associated ancillary site works / 0.8 km away / 03 June 2026Conditional grant