23148: For development of a wind farm in the townlands of Fahy Beg, Fahy More North, Ballymoloney, Ballyknavin (Ed O'Briensbridge), Balllyquin More, Woodpark and Leitrim, Co Clare together with the development of an underground grid connection cable to the national grid. The underground grid connection is located primarily within the public road within the townlands of Leitrim, Fahy More South, Ballybrack, Aharinaghmore, Tooreen (Ed Cloghera) Aharinaghbeg, Knockdonagh, Roo East, Blackwater, Rosmadda West, Parkroe, Lackyle (Ed Ballyglass) and Castlebank, Co Clare. Temporary accommodation works to facilitate the delivery of wind turbine components to the site will be required in the townland of Ardataggle, Co Clare. The development will consist of: Construction of 8 no. wind turbines with a blade tip height range from 169m to 176.5m, a hub height range from 102.5m to 110m and a rotor diameter range from 131m to 138m; Erection of 1 no. permanent meteorological mast to a height of 100m above ground level; Construction of 1 no. onsite 38kV electrical substation to ESB Networks (ESBN) specifications and associated compound including Welfare facilities, Electrical infrastructure, Parking, Wastewater holding tank, Rainwater harvesting tank, Security fencing and all associated infrastructure, services and site works including landscaping in the townland of Woodpark; Installation of medium voltage electrical and communication cabling underground between the proposed turbines and the proposed on-site substation and associated ancillary works; Construction of turbine foundations and crane pad hardstanding area; Construction of new site tracks and associated drainage infrastructure; Upgrading of existing tracks and associated drainage infrastructure where necessary; Access to the proposed wind farm site will be from the R466 local road and will consist of the use of an existing quarry entrance in the townland of Leitrim which will be upgraded, as well as the creation of 1 no. new permanent site entrance on the Fahymore local road in the townland of Ballyquin More, and the use of 1 no. existing field entrance which will be upgraded, in the townland of Ballymoloney. The site entrances shall be used for both construction and operation of the proposed wind farm; All associated drainage and sediment control; Installation of new watercourse and drain crossings; Reuse and upgrading of existing internal watercourse and drain crossings; 2 no. temporary construction site compounds and
Fahy Beg Fahy More North Ballymoloney Ballyknavin (Ed O'Briensbridge) Ballyquin More, Woodpark Leitrim Fahy More South Ballybrack Aharinaghmore Tooreen, (Ed Cloghera) Aharinaghbeg Knockdonagh Roo East Blackwater Rosmadda West Parkroe Lackyle (Ed
DecisionRefused
Decided03 May 2023
Application typePERMISSION
Source documents6
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason
No refusal reason is on record for this application yet.
Conditions
No conditions
No conditions are on record for this application yet.
Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on www.eplanning.ieSource portal
- Notification Of DecisionSource: clarecoco.eplanning.ie / 6d5fa4a0-614f-456d-b2f9-ee6a749a5888.pdf / Document 664473Source PDF
- Chief Executives OrderSource: clarecoco.eplanning.ie / Acbc2afa-bb95-4b6c-a227-21f886e8fd5b.pdf / Document 664472Source PDF
- Final GrantSource: clarecoco.eplanning.ie / 4f192feb-ee01-4b08-bf67-f7bbd79c0d54.pdf / Document 732196Source PDF
- Planners ReportSource: clarecoco.eplanning.ie / D0f18f55-da03-41ef-989e-f2201ba9b71c.pdf / Document 664470Source PDF
- Planners ReportSource: clarecoco.eplanning.ie / 59560772-d37b-477a-8bc8-1255d2e6ea73.pdf / Document 664478Source PDF
Nearby precedent
Similar nearby applications linked to this planning decision.- 2460603For development at the existing Ballyquin Quarry. The development will consist of: (i) The extraction of sand from an area of approximately 16.3 hectares within an overall site area of 97.5 hectares; (ii) The infill and restoration of existing and future quarry voids (38 hectares) using inert soil and stone waste (imported inert greenfield and non-greenfield soils and stone, and river dredge spoil) which will be a soil recovery facility and require a waste management licence or soil and stone by-product (i.e. essentially virgin soil or equivalent to virgin soil and stone, and river dredge spoil) which will be notified to the Environmental Protection Agency (EPA) as an Article 27 by-product; (iii) The upgrade of existing quarry infrastructure including site office, weigh bridge, wheelwash, and welfare facilities; (iv) Refuelling area and associated drainage works, comprising 1 No. concrete hardstand area, hydrocarbon interceptor, wetland, inspection chamber and soakaway; (v) 1 No. soil inspection shed (c.875q. m) for the inspection of soil material; (vi) Erection of washplant; (vii) Settlement ponds; (viii) Landscape berms and fencing; (ix) All associated ancillary works. Site access is via the existing entrance off the R466. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) have been prepared in respect of the proposed development. Should the inert soil, stone and inert dredge spoil materials be deemed to be a waste, then a Waste Management Licence will be required under Part 5 of the Waste Management Act 1996 (as amended) and an application for a Waste Management Licence will be made to the EPA following a grant of planning permission for the proposed development. / 0.8 km away / 01 September 2025Refused
- 23596For to demolish old "outhouses", extend existing dwelling house, install an effluent system, new entrance and all associated site works / 1.9 km away / 29 January 2024Refused
- 19711To construct a new single storey house, complete a new domestic garage, effluent treatment system and a new site entrance / 2.1 km away / 24 October 2019Refused
- 19417For the construction of a log cabin single storey dwelling, new entrance, onsite waste water treatment system, bored well, together with all associated incidental boundary and site works / 2.6 km away / 15 October 2019Refused
- 24150To fill the existing poor quality agricultural land with stone and soil in order to raise the level of the ground, including all ancillary site works / 2.9 km away / 01 July 2024Refused
- 2460411The development will consist of: (i) The construction of 7 no. wind turbines with the following parameters: a. Total tip height range of 179.5m – 180m, b. Rotor diameter range of 149m – 155m, c. Hub height range of 102.5m to 105m, (ii) Construction of associated foundations, hardstand and assembly areas; (iii) All associated wind farm underground electrical and communications cabling connecting the turbines and mast to the proposed electrical substation; (iv) Construction of 1 no. permanent 38kV electrical substation including a single-story control building with welfare facilities, all associated electrical plant and equipment, security fencing, entrance on to new access road, all associated internal underground cabling, drainage infrastructure, wastewater holding tank, retention separator tank, and all ancillary works, in the townland of Killeagy (Goonan), Co. Clare; (v) A Battery Energy Storage System within the 38kV electrical substation compound; (vi) 1 no. permanent meteorological mast of c. 36.5m in height, associated foundation and hard-standing area in the townland of Shannaknock; (vii) The permanent upgrade of 1 no. existing site entrance off the L7080 (‘The Gap Road’) for the provision of construction and operational access; (viii) Provision of 3 no. new permanent site entrances off the L7080 for the provision of construction and operational access; (ix) Provision of 3 no. new temporary site entrances off the L7080 for the provision of construction access; (x) Upgrade of existing tracks/ roads, including the L7080, and the provision of new site access roads, 4 no. watercourse crossings, junctions and hardstand areas; (xi) 1 no. temporary construction compound with temporary offices and staff facilities in the townland of Killeagy (Goonan); (xii) 1 no. temporary storage area in the townland of Killeagy (Goonan); (xiii) 1 no. borrow pit in the townland of Killeagy (Goonan); (xiv) Peat and Spoil Management; (xv) Tree Felling to accommodate the construction and operation of the proposed development; (xvi) Operational stage site and amenity signage; and (xvii) All ancillary apparatus and site development works above and below ground, including soft and hard landscaping and drainage infrastructure. A 10-year planning permission and 35-year operational life of the wind farm from the date of commissioning of the entire wind farm is sought. A Design Flexibility opinion issued by Clare County Council on 22nd April 2024 accomanies this application. The de / 3.1 km away / 23 October 2024Refused
- 2360370For the construction of a detached single storey dwelling, detached domestic garage, new entrance, onsite wastewater treatment system, bored well, together with all associated ancillary and incidental site works / 3.2 km away / 16 April 2024Refused
- 19584To construct a two storey dwelling over basement, site entrance, waste water treatment system and all associated site works / 3.7 km away / 06 September 2019Refused