17227: Alterations to a previously granted permission Ref PL16/73 to include a new 134m2 single storey office extension to our premises plus all associated signage and site works.
Muinebheag Business Park, Royal Oak Road, Bagenalstown
DecisionConditional grant
Decided17 November 2017
Application typePERMISSION
Source documents1
Site
What is on file
0refusal reasons0conditions8nearby records
Decision details
Core application dates and identifiers from the public planning record.Planning analysis
Refusal reasons and planning conditions extracted from the public decision file.Refusal reasons
No refusal reason
No refusal reason is on record for this application yet.
Conditions
No conditions
No conditions are on record for this application yet.
Source documents
Original council portal records and source PDFs where available.- Application fileApplication file on www.eplanning.ieSource portal
Nearby precedent
Similar nearby applications linked to this planning decision.- 22249The installation of solar photovoltaic panels mounted to roof of existing portal frame building and all associated site works / 0.1 km away / 20 September 2022Conditional grant
- 22402For (a) the erection of 3 no. water tanks having maximum height of 12 meters above ground level. (b) the relocation of 2 no. existing grain silos and all associated site works / 0.1 km away / 13 July 2023Conditional grant
- 2061The construction of an onsite wastewater treatment system, consisting of wastewater pump station, over ground rising main, sludge tank, balance tank, aerobic digester, control room and all associated site works. Retention planning permission is sought for the erection of 2 No grain silos, 2 No gas silos and 4 No Multi-Purpose Vessels with all ancillary site works / 0.1 km away / 23 February 2021Conditional grant
- 20250(a) the change of use for part of existing portal frame building, from recreation centre to light industrial packaging / manufacturing area and visitor area. (b) External and internal alterations to include demolition of existing internal walls and alterations to roof structure and finishes. (c) The construction of an E.S.B. substation to include switch room and all ancillary development works / 0.1 km away / 11 November 2020Conditional grant
- 21160Permission for an extension to existing workshop buildings to be constructed in 2 phases / 0.1 km away / 05 August 2021Conditional grant
- 17232Retention planning permission and planning permission. Retention planning permission consists of the following, a). Retention of existing structure 01 of 24.5m2. b). Retention of existing structure 02 of 464m2. c). Retention of existing substation of 29m2, all to south elevation and Planning permisison will consist of the following, d). Proposed extension to south elevation consisting of 464m2. e). Proposed extension to north elevation with proposed floor area of 2586.5m2 which consists of an extension to existing factory floorand a two storey office block with canteen facilities. f). Proposed MV Substation of 29m2. g).Demolition of existing two storey office block. h). Proposed new entrance to the western boundary. i). Proposed 2.4mt high palisade fencing to new boundary. j). Proposed hardstanding area with associated lighting on 4mt high poles to accomodate new car parking to the south of site, minor interior and exterior alterations and all ancillary site works / 0.2 km away / 15 September 2017Conditional grant
- 17320An extension to existing building consisting of extending existing locker room and new goods inwards/storage area at ground floor level and extending existing office area at first floor level, together with all associated site works. / 0.2 km away / 17 January 2018Conditional grant