Conditional grantDecided 29 September 2020Carlow County Council

2064: Permission for the demolition of an existing single storey extension to be replaced with the construction of a dormer type extension to the rear of our dwelling, the construction of a porch to the front elevation of our dwelling, upgrading works to existing entrance and front boundary, retention permission for a domestic garage / store and all associated site works.

Royal Oak Road, Bagenalstown, Co. Carlow
DecisionConditional grant
Decided29 September 2020
Application typePERMISSION
Source documents4

Site

What is on file

0refusal reasons12conditions8nearby records

Decision details

Core application dates and identifiers from the public planning record.

Planning analysis

Refusal reasons and planning conditions extracted from the public decision file.

Refusal reasons

No refusal reason

No refusal reason is on record for this application yet.

Conditions

  • 1Retain and carry out development in accordance with plans received 26/02/20 and amended by FI response 14/08/20.Compliance
  • 2External wall and roof finishes for extension and porch must match existing dwelling.Design Materials
  • 3Submit elevation drawings for front boundary wall reinstatement to original form/height, plastered and capped; remove partially completed piers prior to commencement.Design Materials
  • 4Do not impair drainage; no surface water to road/adjoining properties; collect/dispose to soakways/system per BS 8301:1985 and BRE Digest 365 with inspection covers.Wastewater Drainage
  • 5Retain and maintain all existing mature trees and hedgerow planting on/bounding the site.Landscaping Boundary
  • 6Sign Irish Water connection agreement prior to commencement; comply with CDS Technical Documentation; subject to Capital Investment Programme constraints.Water Services
  • 7Provide off-carriageway parking during construction; prevent debris on road; maintain neat site; control noise/dust emissions.Construction Management
  • 8Construction hours restricted to Mon-Fri 08.00-18.00 and Sat 08.00-13.00; no Sundays/Bank Holidays without written approval.Construction Management
  • 9Relocate service poles prior to construction; bury all ESB/telecom cables underground at applicant expense.Traffic Access
  • 10Consult Chief Fire Officer prior to commencement and strictly comply with fire safety requirements.Compliance
  • 11Pay development contribution of €461.00 prior to commencement for extension (86.1m² @ €10/m²). Interest applies at 5% p.a.Development Contribution
  • 12Pay development contribution of €608.00 within one month of final grant for garage/store (60.8m² @ €10/m²). Interest applies at 5% p.a.Development Contribution